攀钢2#高炉开炉达产实践
BLOW-IN AND OPERATION FOR PANGANG 2# BLAST FURNACE
-
Abstract: The blow in and operation for Pangang 2# blast furnace were introduced. Based on blow in experience of the past and by means of new technical measures, the utilization coefficient of 2# blast furnace comes up to 1.938 t/(m3·d) 6 days after blowing in.
-
Key words:
- BF ironmaking /
- blow in /
- V-Ti-bearing magnetite
-

计量
- 文章访问数: 69
- HTML全文浏览量: 15
- PDF下载量: 1